DAN BANK STABILISATION WORKS COMPLETE - Monday 6 September 2010
Over the 12 weeks of the works:
There were no delays to bus services.
Stockport Road was open from 6am every morning.
The road was open for the remaining nine weekends once the piling work was successflily completed (every weekend from 10 Jliy until 5 September).
Electronic signs were installed on the approaches to Dan Bank and were updated when the road was schedlied to be closed and then when the road re-opened.
Updates to the website, email update newsletters and SMS text messages were sent to those that subscribed to give up-to-date information about what was happening and the effect on traffic.
ROAD CLOSURE INFORMATION
Dan Bank on Stockport Road (A626) will be closed overnight between
the following morning for 12 weeks from
Monday 14 June until Sunday 5 September 2010.
This road closure will allow strengthening works to take place to stabilise Stockport Road. This will involve piling work to secure the road so that it will remain safe and stable over the long term. There will also be some investigation work into pedestrian facilities and traffic flow at the Stockport Road and Dooley Lane junction.
Below is some important information about what you need to know during road closure. Further information is available about the diversion route, bus service changes and how the Stockport Council is working with the emergency services in the menu bar on the left under Current Situation.
Stockport Council is working hard to ensure that any disruption to commuters, local residents and businesses is kept to a minimum so please read the information on this website and make sure you keep up to date throughout the works.
You can register for updates by either entering your email address on the menu bar to the left or register for free text message updates which will tell you when the road is open or closed. Click here for some more information about this.
|